Villa 12, Al Barari · construction
You see the site the way investors see it. Contractor Desert Build · rating A.
Readiness
52%
3 of 8 milestones confirmed · next Roof
Raised
3.5MAED
100% placed · 212 investors
Released so far
1.0MAED
34% of the 3.0M AED fixed-price contract
Left in escrow
2.0MAED
contract balance for the remaining stages · released only against facts
done: Excavation
3 Jun 2026
done: Foundation
3 Sept 2026
done: Frame
20 Oct 2026
current: Roof
15 Nov 2026
planned: MEP
20 Dec 2026
planned: Finishing
15 Feb 2027
planned: Landscaping
10 Mar 2027
planned: Handover
25 Mar 2027
Milestones and evidence
Each stage is paid from escrow only when the engineer's report and the site oracle agree.
- Done
Excavation
8% of budget · 3 Jun
- Done
Foundation
12% of budget · 3 Sep
- Done
Frame
14% of budget · 20 Oct
- In progress
Roof
10% of budget · 15 Nov
- Planned
MEP
16% of budget · 20 Dec
- Planned
Finishing
22% of budget · 15 Feb
- Planned
Landscaping
8% of budget · 10 Mar
- Planned
Handover
10% of budget · 25 Mar
Latest from the site
- 20 Oct 2026Milestone released — “Frame” confirmed: 14 geophotos, drone pass, engineer act. AED 420,000 released to the contractor
- 15 Oct 2026Vote opened — Holder vote opened: sell at AED 8,500,000 or keep (until 30 Oct)
Holder vote open: Sell at AED 8,500,000 or keep the villa and receive DLD title tokens · closes 30 Oct 2026
Open the investor page for V-012 ›